A1 BLDG MASONRY WORK AT 7TH FLOOR LEVEL IN PROGRESS |
![]() |
A1 BLDG TERRACE FLOOR SLAB COMPLETED |
![]() |
A2 bldg block work at 11th floor in progress |
![]() |
A2 bldg terrace floor slab completed |
![]() |
A3 BLDG 3rd FLOOR SLAB COMPLETED AND 4th FLOOR SLAB SHUTTERING AND REINFORCEMENT WORK IN PROGRESS |
![]() |
B1 BLDG 8TH FLOOR SLAB COMPLETED AND 9TH FLOOR SLAB SHUTTERING AND REINFORCEMENT IN PROGRESS |
![]() |
B1 BLDG MASONRY WORK AT 5TH FLOOR LEVEL IN PROGRESS |
![]() |
C1 bldg 8th floor masonry work in progress |
![]() |
C1 bldg 12th floor slab completed |
![]() |
C2 bldg column above 12th floor slab in progress |
![]() |
C2 bldg column above 12th floor slab in progress |
![]() |
C3 BLDG MASONRY WORK AT 11TH FLOOR LEVEL IN PROGRESS |
![]() |
C3 BLDG TERRACE FLOOR SLAB IN PROGRESS |
![]() |
C4 BLDG TIE BEAM 25% COMPLETED |
![]() |
C4 BLDG U.G. TANK WALL TOWARDS BLDG SIDE IN PROGRESS |
![]() |
D1 BLDG 7TH FLOOR SLAB COMPLETED AND 8TH FLOOR LEVEL IN PROGRESS |
![]() |
D1 BLDG MASONRY WORK AT 5TH FLOOR LEVEL IN PROGRESS |
![]() |
D2 CONCRETING OF FOOTING 15NOs COMPLETED AND BALANCE FOOTING SHUTTERING WORK IN PROGRESS |