A1 BLDG MASONRY WORK AT 7TH FLOOR LEVEL IN PROGRESS

A1 BLDG TERRACE FLOOR SLAB COMPLETED

A2 bldg block work at 11th floor in progress

A2 bldg terrace floor slab completed

A3 BLDG 3rd FLOOR SLAB COMPLETED AND 4th FLOOR SLAB SHUTTERING AND REINFORCEMENT WORK IN PROGRESS

B1 BLDG 8TH FLOOR SLAB COMPLETED AND 9TH FLOOR SLAB SHUTTERING AND REINFORCEMENT IN PROGRESS

B1 BLDG MASONRY WORK AT 5TH FLOOR LEVEL IN PROGRESS

C1 bldg 8th floor masonry work in progress

C1 bldg 12th floor slab completed

C2 bldg column above 12th floor slab in progress

C2 bldg column above 12th floor slab in progress

C3 BLDG MASONRY WORK AT 11TH FLOOR LEVEL IN PROGRESS

C3 BLDG TERRACE FLOOR SLAB IN PROGRESS

C4 BLDG TIE BEAM 25% COMPLETED

C4 BLDG U.G. TANK WALL TOWARDS BLDG SIDE IN PROGRESS

D1 BLDG 7TH FLOOR SLAB COMPLETED AND 8TH FLOOR LEVEL IN PROGRESS

D1 BLDG MASONRY WORK AT 5TH FLOOR LEVEL IN PROGRESS

D2 CONCRETING OF FOOTING 15NOs COMPLETED AND BALANCE FOOTING SHUTTERING WORK IN PROGRESS