PRA's The Lake District, Kondhwa Annexe (Yeolewadi) - Progress as of April 2012
Visit PRA's The Lake District - Progress as of February 2012
Also visit popular post on Residential projects in East Pune
Click here for details on current progress at PRA's East Avenue, Wagholi, Nagar Road
|  | 
| A1 BLDG MASONRY WORK AT 7TH FLOOR LEVEL IN PROGRESS | 
|  | 
| A1 BLDG TERRACE FLOOR SLAB COMPLETED | 
|  | 
| A2 bldg block work at 11th floor in progress | 
|  | 
| A2 bldg terrace floor slab completed | 
|  | 
| A3 BLDG 3rd FLOOR SLAB COMPLETED AND 4th FLOOR SLAB SHUTTERING AND REINFORCEMENT WORK IN PROGRESS | 
|  | 
| B1 BLDG 8TH FLOOR SLAB COMPLETED AND 9TH FLOOR SLAB SHUTTERING AND REINFORCEMENT IN PROGRESS | 
|  | 
| B1 BLDG MASONRY WORK AT 5TH FLOOR LEVEL IN PROGRESS | 
|  | 
| C1 bldg 8th floor masonry work in progress | 
|  | 
| C1 bldg 12th floor slab completed | 
|  | 
| C2 bldg column above 12th floor slab in progress | 
|  | 
| C2 bldg column above 12th floor slab in progress | 
|  | 
| C3 BLDG MASONRY WORK AT 11TH FLOOR LEVEL IN PROGRESS | 
|  | 
| C3 BLDG TERRACE FLOOR SLAB IN PROGRESS | 
|  | 
| C4 BLDG TIE BEAM 25% COMPLETED | 
|  | 
| C4 BLDG U.G. TANK WALL TOWARDS BLDG SIDE IN PROGRESS | 
|  | 
| D1 BLDG 7TH FLOOR SLAB COMPLETED AND 8TH FLOOR LEVEL IN PROGRESS | 
|  | 
| D1 BLDG MASONRY WORK AT 5TH FLOOR LEVEL IN PROGRESS | 
|  | 
| D2 CONCRETING OF FOOTING 15NOs COMPLETED AND BALANCE FOOTING SHUTTERING WORK IN PROGRESS | 
 
 